DETAILS OF THE ORDERS EXECUTED FOR THE ERECTION WORK OF TRANSMISSION LINES & SUB STATIONS DURING LAST FIVE YEARS.

22

Supply, Erection & Commissioning of 220 KV Suthri- Sindhodi Tr. Line.

W.O. no. 4500038638 dated 28/02/07

14

29/10/07

Suzlon Energy ltd

23

Supply & Erection work of 220 KV Gangapur – Valve line

W.O. no. 4500050046 dated 30/03/07

13

30/05/07

Suzlon Energy ltd

24

Supply, Erection & Commissioning of 66 KV Kuchhdi to Bokhira Tr. Line. (Suzlon)

W.O. no. 4500066555 & 4500066568
both dated 24.10.07

8

6 Month from the Date of WO

Suzlon Energy ltd

25

Supply, Erection & Commissioning of 220 KV Adani to 220 KV KV Vandhiya line for Adani Power line- Kutch

W.O. no. APL/Jyoti/VJ/375/07
Dt.12.07.07& APL/131400/VJ/356/07 dtd. 3.07.07

16.250

6 Month from the Date of WO

Adani Power ltd - Kutch

26

Supply, Erection & Commissioning of 66 KV tr. Line from 220 KV Waghodia S/s.
(Suzlon Infrastructure Ltd.)

W.O. no. 4500068377 dated 17.11.07

9.50

25.03.2008

Suzlon Infrastructure Ltd

27

Supply, Erection & Commissioning of 66 KV Tr. Line from 220 KV Waghodia S/s to 66 KV Areva T & D line.

P.O. no. PTIN/1900001241 dated 21.02.08

20

15.07.2008

Areva T & D- Baroda

28

Supply, Erection & Commissioning of 66 KV Sikarpur- Sivlakha line (Suzlon)

W.O. no. 4500066701& 2 both dated 25.10.07

14

6 Month from the Date of WO

Suzlon Infrastructure Ltd

29

Supply, erection & Commissioning of 132 KV Sabarmati  to Airport tr. Line (Torrent Power Ltd- Ahmedabad)

P.O. no. POMD/0334/07-08 dated 24.08.2007

2.50

6 Month from the Date of WO

Torrent Power Ltd- Ahmedabad

30

Supply, Erection & Commissioning of 220 KV Vandhiya to Shivlakha line (Vestas RRB )

P.O. no. 55372 & 73  both dated
11.01.08

23

MAY -2008

Vestas RRB - Chennai

31

Supply, Erection & Commissioning of 220 KV Vandhiya to Shivlakha line (Vestas RRB )

P.O. no. 55372 & 73  both dated 11.01.08

23

MAY -2008

Vestas RRB - Chennai

32

Survey & Route Alignment work of 400 KV / 220 KV Transmission lines Using Modern Technique.

TRII/Survey/2081/400/220KV/Jyoti/143dated 26.12.2007

507.00

Six month from the date of W.O.

Gujarat Energy Transmission Corporation Ltd.

33

Supply ,Erection & Commissioning  work of 220 KV Karad- Peth – GudePanchgini  Project(Suzlon)

W.O. no. 4500053984 dated 25.05.07

36

5.06.2008

Suzlon Energy ltd

34

Supply, erection, testing and commissioning of 2 nos of 220 KV feeder Bays for KIM at existing 220 KV Switchyard of Utran Power station on EPC basis

W.O. CE (Pro.)/SE/V/AT/Erect/Utran/
4900 dated 26.06.08
W.O. CE (Pro.)/SE/V/AT/Supply/Utran/
4901 dated 26.06.08

2 nos of 220 KV Bay S/s

November-08

Gujarat Energy Transmission Corporation Ltd

 